Filters

São Jacinto Camping Project: Court of Auditors Awaits Clarifications from Municipality

06.05.2026 17:17 1 min 1 source РУС
NotíciasdeAveiro.pt POR
São Jacinto Camping Project: Court of Auditors Awaits Clarifications from Municipality
Original source: NotíciasdeAveiro.pt

The Portuguese Court of Auditors has been waiting since January 7, 2026 for documents from the Aveiro municipality regarding the contract for the renovation of the municipal campsite in São Jacinto. The municipality has not yet submitted the requested documents, including proof of multi-year expenditure authorization and financial availability for 2026. The contract was received by the Court on December 19, 2025 for prior review. Mayor Luís Souto attributed delays to interactions with the Court, noting the process takes time.

Suggest news or event

Sent to "Submissions" for moderation

All suggestions go through automated checks and moderation. We publish excerpts and a link to the original source. By submitting you agree to Copyright Holders, Terms, Privacy Policy and Cookies.

→ Glossary